Correct Work Order Operation Dates in NetSuite 2024.2

In NetSuite 2024.2, work order operation dates adjust based on working hours, improving scheduling accuracy.

·2 min read·NetSuite 2024.2·From NetSuite Release Notes PDF

Starting in NetSuite 2024.2, enhancements to how work order operation start and end dates are calculated have been introduced. This update refines the scheduling of manufacturing operations by taking into account whether the operations are completed during working or non-working days. This feature is crucial for manufacturing businesses aiming to manage production schedules effectively.

Key Changes in Operation Date Calculation

Previously, operation start times were strictly aligned with the work order production start date, and the end times were determined by the total duration of setup and run times without consideration for the business’s working calendar.

With the updates in 2024.2, the following guidelines now apply:

Completion on Working Days

  • Operation Start: The operation now begins at the start of the scheduled working day according to the working calendar.
  • Operation End: The remaining operation time is added to the start date. If this duration exceeds available working time, the excess time is rolled over to the following working day.

Completion on Non-Working Days

  • Operation Start: Similar to working days, the operation is set to start at the beginning of the next working day as plotted in the working calendar.
  • Operation End: Remaining operation time is added to the start of the next illustrated working day.

Example Scenario

For instance, if an operation is set to start on a Wednesday but requires 16 hours of working time and Wednesday only has 8 hours available, the operation will finish on Thursday.

This improved scheduling facilitates enhanced resource management and production efficiency, ensuring that all operations are completed promptly while effectively using the work calendar.

Who This Affects

  • Manufacturing Administrators: Responsible for setting up and managing work orders.
  • Supply Chain Managers: Need to oversee the entire production scheduling process.
  • Production Supervisors: Directly involved in the daily operations on the shop floor.

Key Takeaways

  • The calculation of work order operation dates now accounts for working and non-working days in NetSuite 2024.2.
  • Enhanced scheduling reduces the potential for production delays, contributing to efficiency.
  • Administrators and managers in manufacturing sectors will notably benefit from these changes to manage operations better.
Source: Correct Work Order Operation Start and End Dates NetSuite Release Notes PDF. This article was generated from official Oracle documentation and enriched with additional context and best practices.