NetSuite CPQ Template Assemblies Get Separate BOMs

CPQ Configurator 2.1.2 copies template BOMs when Advanced Bill of Materials is enabled and the item creation record’s BOM box is unchecked.

·3 min read·NetSuite 2026.2·View Oracle Docs

NetSuite CPQ Configurator version 2.1.2 copies a template assembly’s BOM to each new assembly instead of sharing it, provided Advanced Bill of Materials is enabled and the item creation record’s Bill of Materials box is unchecked. The new assembly’s BOM can then be edited without modifying the template’s BOM.

What Changes for Template-Based Assemblies?

Item creation records can automatically create assemblies required by a configurable item when a user submits the configuration. Under the two documented conditions, a newly created assembly no longer shares its template assembly’s bill of materials. CPQ Configurator copies that BOM to the new assembly instead.

The practical distinction is where subsequent edits apply: changing the new assembly’s BOM does not modify the template’s BOM. For teams maintaining reusable assembly templates, this provides a way to make configuration-specific BOM changes without changing the template BOM.

What Prerequisites and Settings Apply?

Install NetSuite CPQ Manufacturing to automatically create assembly items required by a configuration. The BOM-copying behavior is documented for NetSuite CPQ Configurator version 2.1.2 and requires both conditions below.

SettingRequired stateRole in this behavior
Advanced Bill of MaterialsEnabled in the accountOne of the two required conditions; also allows assemblies to use an advanced BOM.
Bill of Materials checkboxUnchecked on the item creation recordThe second required condition for copying the template BOM.

Do not treat this as a change to every assembly creation scenario. The source does not describe the resulting template-BOM relationship when either condition is absent.

With Advanced Bill of Materials enabled, select assembly as the item type. Without that feature, the available type is assembly/bill of materials, and assemblies with an advanced BOM cannot be created.

How Should You Prepare Item Creation Records?

The documented assembly setup sequence includes these steps:

  1. Create an item creation record and complete its basic fields.
  2. Set the bill of materials and revision fields.
  3. Add components to the assembly.
  4. Set the manufacturing routing fields.
  5. Add routing steps to the manufacturing routing.

For advanced BOMs, item creation records support setting fields for both the BOM and its revision. If updating an existing BOM, retain the same name on the item creation record. When adding a new BOM to an assembly, an existing standard or master-default BOM will be overwritten. Review existing assignments before testing that operation; copying a template BOM and replacing an existing BOM warrant separate checks.

What Should You Verify After Configuration Submission?

As a validation practice, use a test configuration with a template assembly after checking both qualifying settings. Inspect the resulting assembly’s BOM, then edit that copy and confirm that the template BOM remains unchanged. This checks the documented independence rather than merely confirming that an assembly was created.

For related testing topics, see automatic availability of newly created items and CPQ transaction file attachments.

Who This Affects

  • Administrators: Check the CPQ Manufacturing prerequisite and Advanced Bill of Materials setting.
  • CPQ implementers: Review template-based item creation records and the Bill of Materials checkbox.
  • Manufacturing teams: Test edits to generated BOMs without modifying template BOMs.

Key Takeaways

  • Template-based assemblies receive copied BOMs when both documented conditions are met.
  • Edits to the new assembly’s BOM do not modify the template’s BOM.
  • CPQ Manufacturing is required for automatic assembly creation.
  • Retain BOM names when updating existing BOMs, and review existing assignments before adding a new BOM.

Frequently Asked Questions (4)

What settings make CPQ copy a template assembly’s BOM to a newly created assembly?
The behavior is documented for NetSuite CPQ Configurator 2.1.2 when Advanced Bill of Materials is enabled and the item creation record’s Bill of Materials box is unchecked. Under those conditions, CPQ copies the template BOM to the new assembly instead of sharing it.
Do I need NetSuite CPQ Manufacturing to create assemblies automatically from a configuration?
Yes. NetSuite CPQ Manufacturing is required to automatically create assembly items needed by a configuration. The BOM-copying behavior also requires the documented Advanced Bill of Materials and item creation record settings.
If I edit the generated assembly’s BOM, will the template BOM change too?
No. When the documented conditions are met, the new assembly receives a copied BOM. Subsequent edits to that assembly’s BOM do not modify the template’s BOM.
What should I check before adding a new BOM to an assembly through an item creation record?
Review existing BOM assignments first. When adding a new BOM to an assembly, an existing standard or master-default BOM will be overwritten; when updating an existing BOM, retain the same name on the item creation record.

Weekly Update History (1)

NetSuite CPQadded

Added the following entries: Create Template-Based Assemblies with Independent BOMs Clear Single-Row QTables

View Oracle Docs
Source: Create Template-Based Assemblies with Independent BOMs — Oracle NetSuite Help Center. This article was generated from official Oracle documentation and enriched with additional context and best practices.

Was this article helpful?

More in NetSuite CPQ

View all NetSuite CPQ articles →

Also from NetSuite 2026.2

View all NetSuite 2026.2 changes →