Simultaneous Start of Multiple Operations in NetSuite 2026.1
NetSuite 2026.1 improves scheduling and resource optimization by ensuring operations start simultaneously.
Starting in NetSuite 2026.1, the process for starting multiple operations linked by the Start-to-Start connection type has been refined. Previously, these operations would initiate at nearly the same time but with a minimal lag automatically calculated. With the new update, all operations sharing the same working hours will now start at precisely the same moment when no lag is defined.
Impact on Work Order Scheduling
When using the Start-to-Start connection type:
- If there are no defined lags and operations share the same working hours, they begin simultaneously.
- If these operations follow previous ones, they are connected following the same principles as before, adhering to defined connection types and any scheduled lag.
Additionally, the scheduling of subsequent operations linked by Start-to-Start will depend on the type of scheduling used in the Work Order, whether it’s Forward or Backward scheduling. This flexibility allows for more precise manufacturing operation management.
Benefits of Operations Overlap
These changes offer several advantages:
- Improved Efficiency: By allowing simultaneous starts, the timeline for work orders can be significantly reduced, enhancing overall productivity.
- Resource Optimization: Better scheduling helps utilize manufacturing resources more effectively, minimizing downtime between operations.
Configuration Requirements
To utilize the new simultaneous operations feature, ensure that the following features are enabled:
- Assembly Items
- Work Orders
- Manufacturing Work In Process
- Manufacturing Routing and Work Center
For details on setting up operations overlap, including how to select connection types and lag amounts, consult the appropriate topics in the documentation.
Frequently Asked Questions (4)
What prerequisites must be met to use the simultaneous start of operations in NetSuite 2026.1?
How does the simultaneous start feature interact with Forward and Backward scheduling types?
Does the simultaneous start feature apply to operations that have a lag defined?
How does this feature affect existing operations that begin following the completion of previous ones?
Weekly Update History (1)
Was this article helpful?
More in Manufacturing
- Approval Rule Validation Process in SuiteApprovals
Approval Rule Validation in SuiteApprovals ensures consistent enforcement based on uniqueness, priority, and saved search criteria.
- Manufacturing Mobile Enhancements in NetSuite 2026.1
Manufacturing Mobile enhancements in NetSuite 2026.1 improve usability for operators with new features for reporting operations and component consumption.
- Forward and Backward Scheduling in NetSuite 2026.1
Discover how forward and backward scheduling in NetSuite 2026.1 enhances manufacturing efficiency and optimizes planning.
- Leave Operation Feature Enhances Efficiency in NetSuite 2026.1
Leave Operation feature enhances workflows in NetSuite 2026.1, allowing operators to manage tasks flexibly.
Also from NetSuite 2026.1
- NetSuite CPQ Functions Overview and Usage in 2026.1
NetSuite CPQ 2026.1 introduces a comprehensive list of functions, optimizing both client-side and server-side operations for better governance and...
- Enhancements to Custom Tool Scripts in NetSuite 2026.1
NetSuite 2026.1 improves custom tool scripts with execution logs, management page, and binary file support. TL;DR Opening
- Unlimited Sandbox Refreshes in NetSuite 2026.1
NetSuite 2026.1 introduces unlimited sandbox refreshes and changes access for OCI configurations.
- Enriched Bank Data for Improved Transaction Matching in NetSuite
Updated for NetSuite 2026.1: Enriched Bank Data feature enhances transaction matching accuracy using generative AI.
Advertising
Reach Manufacturing Professionals
Put your product in front of NetSuite experts who work with Manufacturing every day.
Sponsor This Category